Aimed
at detection and prioritization of causes of delay in dry bulk cargo
loading/unloading operation at the relevant terminal of Latakia port of Syria,
the present research has been conducted by use of PROMETHEE method in three
stages. In the first stage, the number of lags and halts in loading/unloading
operation (hereinafter referred to as L/U operation) and the involving causes
during a specific period were studied. As well, brain storming cessions
attended by experts from the mentioned terminal were held during which
seventeen numbers of causes of delay were detected. Then, based on the criteria
of determination of causes occurrence probability (occurrence frequency), the
extent of causes impact on process after occurrence (severity) and probability
of detection of causes before having impact on the process (detection), the
causes were scored in form of a scale ranging from 1 to 10. In the second
stage, using AHP method, the mentioned criteria were weighted. The criterion of
occurrence probability was the most weighted (0.43) and the criterion of
detection probability was the least weighted (0.26). Based on the obtained
scores by each one of the causes, the matrix of decision making was formed and
the mentioned causes were ranked by use of PROMETHEE method.
Website: http://www.arjonline.org/business-and-management/american-research-journal-of-business-and-management/
Website: http://www.arjonline.org/business-and-management/american-research-journal-of-business-and-management/
No comments:
Post a Comment